Campus construction update for October 2025

Halfway through the fall semester, you will notice ongoing and new construction across Wichita State University’s 330 acres and beyond.

Wilkins Stadium

Construction is complete on the indoor softball practice facility adjacent to Wilkins Stadium. Inside the building is a netted softball infield that is divisible into batting and pitching practice areas.

Exterior work continues on the north side of the new building where the outdoor batting cages will be relocated in preparation for construction of the softball team and operations building to the south of the new building.

Corbin Education Center

Work is complete in Corbin Education Center – all displaced faculty and staff have moved back into their offices in the building. Classes are scheduled to resume in the building in the spring semester.

Ablah Library

Repairs are complete in the basement of Ablah Library and the space reopens to the public this week.

University Stadium Phase 1A/1B

Construction is underway for Phase 1B of the University Stadium (formerly Cessna Stadium). This phase of construction consists of widening the field to hold a regulation-sized artificial turf soccer field and installing a nine-lane track and internal stadium sidewalks that will connect the east and west sides of the facility inside of the fence.

Improvements to the throwing area south of Charles Koch Arena are also underway. A storage building is under construction. Additions also include a longer javelin runway and warmup lanes. Shot put competition will move to this area from inside the stadium.

Construction is anticipated to continue through the fall semester.

Brennan I, II and III demolitions

Demolition of the three buildings is underway. TRIO/Upward Bound staff have relocated to their new home in Grace Wilkie Hall/Grace Wilkie Annex. The demolition project is anticipated to be complete by the end of November.

Grace Wilkie Hall/Grace Wilkie Annex roof replacement

A roof replacement project is scheduled for October/November. Fencing will be installed around the perimeter of the building as work progresses.

Henrion Hall HVAC improvements Phase 3 and 4

Construction has begun in Henrion Hall for a project to provide air conditioning to the remainder of the building following recent projects in the sculpture and ceramics classroom areas as well as relocating and expanding the wood shop.

The project will be phased to allow the building to remain occupied but will affect building entrances throughout the year. Construction is anticipated to be completed in time for the Fall 2026 semester.

Morrison Hall

Construction is underway in Morrison Hall on a project to replace the elevator and update the finishes/ceiling/lighting on the first floor of the building. The first floor and elevator are anticipated to be open to the public in February 2026.

NIAR Hub for Advanced Manufacturing Research

Construction on the NIAR HAMR building continues to progress. Construction is expected to be complete by the end of 2025.

The 170,000-square-foot building is partly funded by an EDA grant and will house advanced manufacturing research labs and associated offices.

The building is located on Innovation Boulevard between the Partnership Building 1 and The Suites. The first floor is primarily labs with offices on the second floor.

Partnership Building 3B

P3B, located between Partnership Building 3 and The Smart Factory @Wichita, is under construction. It will house the Forensic Crime Gun Intelligence Laboratory for the Bureau of Alcohol, Tobacco, Firearms and Explosives (ATF). The building is expected to be complete early in spring 2026.